Trending...
- Slotozilla Reports Strong Growth in Q2 2026
- Targeted Web Traffic Announces Wisconsin Website Design Services
- Where Do Missouri Plane Crashes Really Happen? Not Where You'd Think
Responsible Energy Alliance alleges that ATC's application remains incomplete and still violates Wisconsin's law requiring that, absent extenuating circumstances, new transmission lines must be routed along existing utility corridors
PORT WASHINGTON, Wis. - WisconsinEagle -- The Responsible Energy Alliance, a citizen coalition ("REA"), filed an expedited motion Monday with the Public Service Commission of Wisconsin ("PSC"), asking the regulatory agency to revoke its December 15, 2025, determination that American Transmission Company's ("ATC") application to build new extra-high-voltage transmission lines through ecologically sensitive greenfields in western Ozaukee and eastern Washington counties was complete.
The motion, filed by REA's counsel, Erik S. Olsen of Eminent Domain Services, LLC, points to sworn testimony by ATC's own customer submitted in the case. In that testimony, Vantage's Vice President of New Site Development agrees with the Responsible Energy Alliance in supporting routing that avoids the sensitive greenfields in Ozaukee and Washington Counties. Tracye Herrington, Vice President of New Site Development for Vantage Data Centers Management Company, LLC, the sole customer the new lines would serve, testified that, after reviewing the routing alternatives, "Vantage has publicly expressed support for selection of the South Alternate Route." The South Alternate Route avoids the sensitive greenfields that the Responsible Energy Alliance is fighting to preserve.
More on Wisconsin Eagle
REA's motion argues that ATC has never explained why its preferred and preferred-contingent routes - the two greenfield routing options - depart from that priority to instead cut new corridors through ecologically sensitive greenfields. A route largely following ATC's own existing right-of-way remains on the table - an alternative that, per Vantage's own testimony, would still meet the project's technical and operational requirements.
The motion includes ATC's own project map, which REA says labels the disputed segment "new transmission line build and replace," undercutting ATC's argument in discovery that the segment should be treated as equivalent to a greenfield route.
The motion also points to the Wisconsin Department of Agriculture, Trade and Consumer Protection, which recommended in its statutorily required Agricultural Impact Statement that the PSC approve the South Alternate Route - the route that avoids the greenfield segments - because of its lower impact on prime agricultural land, hydric soils, and existing farmland preservation and managed forest land programs.
REA's motion is also supported by testimony from wildlife biologist Dr. Gary Casper, who states that routing the lines through either greenfield option "most definitely will cause harm, there is no question about that," and that "neither the Preferred or Preferred-Contingent routes are acceptable."
Dr. Casper's testimony further explains that the project's compressed timeline has not allowed adequate seasonal survey work - noting, for example, that confirming the presence of a federally endangered dragonfly species in the project area requires verification during its July-August flight season, a step that has not yet occurred. Dr. Casper recommends that ATC withdraw the preferred and preferred-contingent proposals and use the existing right-of-way for the alternative route instead.
More on Wisconsin Eagle
REA's motion asks the PSC to take one of two actions: either revoke its completeness determination outright and require ATC to reapply or, alternatively, order ATC to file a revised application that permanently withdraws the preferred and preferred-contingent greenfield segments from consideration.
REA says the motion is time-sensitive: the deadline for parties to file direct testimony in the case is Friday at 1:30 p.m., with hearings currently scheduled for August 25-28. REA argues that timeline is not workable while the unresolved greenfield routing question remains on the table.
"Friday's confusing filings by ATC only underscored that this application was never complete in the first place," Olsen said. "But what should put this beyond doubt is that ATC's own customer has told the PSC, under oath, that the alternative route which avoids the sensitive greenfields works perfectly well for Vantage. Why are ecologically sensitive greenfields even being considered for such massive transmission lines when Vantage itself seems perfectly fine with the route that spares these special lands and follows Wisconsin law? I just don't get it."
If the PSC agrees to revoke its completeness determination, ATC would have to file a new application, restarting the review process. ATC asserts that the up-to-360 day delay caused by refiling would be problematic. REA says that outcome is not a delay opponents should fear, but rather the process protection Wisconsin law is supposed to provide for a project of this size and cost.
The motion, filed by REA's counsel, Erik S. Olsen of Eminent Domain Services, LLC, points to sworn testimony by ATC's own customer submitted in the case. In that testimony, Vantage's Vice President of New Site Development agrees with the Responsible Energy Alliance in supporting routing that avoids the sensitive greenfields in Ozaukee and Washington Counties. Tracye Herrington, Vice President of New Site Development for Vantage Data Centers Management Company, LLC, the sole customer the new lines would serve, testified that, after reviewing the routing alternatives, "Vantage has publicly expressed support for selection of the South Alternate Route." The South Alternate Route avoids the sensitive greenfields that the Responsible Energy Alliance is fighting to preserve.
More on Wisconsin Eagle
- Jeff Schreiber Returns to The Retirement Advantage, Inc. (TRA)® as VP of National Distribution
- Chosen's Gala gets a New Look: Join us at Chosen's Open Hearts, Open Homes Brunch
- He Fell in Love With AI, Quit His Job, and Turned the Relationship Into Research
- Nearly One-Third of CRE Asset Managers Make Major Capital Decisions on Gut Instinct, New Survey Finds
- RemoteBridge Names Dr. John N. Just, Ed.D. Chief Executive Officer
REA's motion argues that ATC has never explained why its preferred and preferred-contingent routes - the two greenfield routing options - depart from that priority to instead cut new corridors through ecologically sensitive greenfields. A route largely following ATC's own existing right-of-way remains on the table - an alternative that, per Vantage's own testimony, would still meet the project's technical and operational requirements.
The motion includes ATC's own project map, which REA says labels the disputed segment "new transmission line build and replace," undercutting ATC's argument in discovery that the segment should be treated as equivalent to a greenfield route.
The motion also points to the Wisconsin Department of Agriculture, Trade and Consumer Protection, which recommended in its statutorily required Agricultural Impact Statement that the PSC approve the South Alternate Route - the route that avoids the greenfield segments - because of its lower impact on prime agricultural land, hydric soils, and existing farmland preservation and managed forest land programs.
REA's motion is also supported by testimony from wildlife biologist Dr. Gary Casper, who states that routing the lines through either greenfield option "most definitely will cause harm, there is no question about that," and that "neither the Preferred or Preferred-Contingent routes are acceptable."
Dr. Casper's testimony further explains that the project's compressed timeline has not allowed adequate seasonal survey work - noting, for example, that confirming the presence of a federally endangered dragonfly species in the project area requires verification during its July-August flight season, a step that has not yet occurred. Dr. Casper recommends that ATC withdraw the preferred and preferred-contingent proposals and use the existing right-of-way for the alternative route instead.
More on Wisconsin Eagle
- Project CIVICA Report Finds 10,680 Non-Citizen Indicators on New York Voter Rolls — Including 88 Records with Recent Voting History
- New Analysis Details Three Converging Forces in AI and Workforce Policy Behind a $37 Billion GDP Reduction
- Revenue Optics Launches Pricing and Revenue Growth Management Practice, Names Shafohi Alamgir Vice President
- Popular AI planner Voiset launches version 2.0 and enters MENA at LEAP 2026 with full Arabic support
- CasaPerks and CredHub Partner to Help the Multifamily Industry Strengthen Resident Activation Through Credit-Building Rewards
REA's motion asks the PSC to take one of two actions: either revoke its completeness determination outright and require ATC to reapply or, alternatively, order ATC to file a revised application that permanently withdraws the preferred and preferred-contingent greenfield segments from consideration.
REA says the motion is time-sensitive: the deadline for parties to file direct testimony in the case is Friday at 1:30 p.m., with hearings currently scheduled for August 25-28. REA argues that timeline is not workable while the unresolved greenfield routing question remains on the table.
"Friday's confusing filings by ATC only underscored that this application was never complete in the first place," Olsen said. "But what should put this beyond doubt is that ATC's own customer has told the PSC, under oath, that the alternative route which avoids the sensitive greenfields works perfectly well for Vantage. Why are ecologically sensitive greenfields even being considered for such massive transmission lines when Vantage itself seems perfectly fine with the route that spares these special lands and follows Wisconsin law? I just don't get it."
If the PSC agrees to revoke its completeness determination, ATC would have to file a new application, restarting the review process. ATC asserts that the up-to-360 day delay caused by refiling would be problematic. REA says that outcome is not a delay opponents should fear, but rather the process protection Wisconsin law is supposed to provide for a project of this size and cost.
Source: Responsible Energy Alliance
0 Comments
Latest on Wisconsin Eagle
- Responsible Energy Alliance Redoubles Initiative to Protect Communities, Lands in Wisconsin Counties
- 5X Gross Margin Improvement to Beat EPS Consensus; $54.6 Million 10-Year Contract Award Puts Cybersecurity Leader on Path to a $30 Million Run Rate
- Independent Colbert Packaging Thrives Amid Industrywide Consolidation
- Free Commercial Glass Estimating and Code Compliance Tools Launched by Landmark Construction - The Leading Glass Company in Los Angeles
- Tallahassee Million-Dollar Home Sales Rise in 2026 as Median Selling Time More Than Doubles
- Slotozilla Reports Strong Growth in Q2 2026
- Flexible Plan Investments Names Carl Resnick President
- Paula Josephine Sadler Releases "Imagine" on 24th Anniversary of Sobriety
- Ritz-Carlton Residences Houston Generates Strong Early New Construction Sales at 2120 Post Oak Blvd
- No Sugar Baker Continues National Growth with Seattle Market Expansion Across Washington, Idaho, and Alaska
- The Refugee Archive Launches Campaign to Preserve 21 Female-Headed Household Oral Histories in Rebel-Controlled Goma
- Space Ambitions Expanding as New Testing Builds on NASA Results and Targets MEO, GEO and Next-Generation Orbital Markets: Ascent Solar Technologies
- FDA Path Clears, Manufacturing Ramps Up + $22.3 Million Strengthens the Balance Sheet; Inflection Point for NRx Pharmaceuticals (N A S D A Q: NRXP)
- Buy Retatrutide Research Peptide: Why Reta Is Getting So Much Attention
- San Diego Attorney Anthony Z. Vargas Narrows Practice to Employment Law, Representing Employees Only
- Solid Earth Introduces RealtyID, a Universal Identity Spine for the Real Estate Industry
- New Memoir Takes Readers Along on a Post-Retirement Travel Journey
- BlazeHive's AI SEO Agent Outranks Human Writers on 500+ Google Top-3 Results in 5 Months, on Autopilot
- Phinge Exposes Massive AI Security Risks, Claiming Its Patented Hardware-Verified Architecture Is The Only Safeguard Against Surveillance Capitalism
- Phinge & CEO Robert DeMaio Publicly Declare Cash Settlements or Judgments Alone Cannot & Will Not Remedy the Deep Public Harm of Infringing Its IP